Suncoast High Replacement

  Project Data
Project Number 0151-7511
School Type High School
Project Type Modernization
Student Occupancy Date 08/16/2010
Site Size 70.00Acres 
Square Footage 291,520 sq. ft.
Student Stations 1,790
Proj Delivery Method CM @ Risk
Construction Manager Suffolk
Architect MPA Architects
Planner Randall Granberry
Sr.Proj Administrator Glen Armbruster
Start Date (NTP) Phase 1 06/18/2007
Phase 2 12/05/2007
Phase 3 11/25/2008
Phase 4 02/08/2010
Duration Phase 1 70
Phase 2 685
Phase 3 405
Phase 4
Days Expended Phase 1 70
Phase 2 884
Phase 3 518
Phase 4 343
% of Time Expended Phase 1 100 %
Phase 2 100 %
Phase 3 100 %
Phase 4 0 %
% Complete Phase 1 100 %
Phase 2 100 %
Phase 3 100 %
Phase 4 100 %
Substantial Completion    Phase 1 08/27/2007
Phase 2 05/08/2010
Phase 3 04/27/2010
Phase 4 01/17/2011
Final Completion Phase 1 09/27/2007
Phase 2 05/31/2011
Phase 3 05/31/2011
Phase 4 05/31/2011
600 W. 28th St. | Riviera Beach | FL | 33404

 

> To View Project Photos Click Here
  Opens New Window
  (Close window to return to this page)

> To View Community Meetings Click Here
  Opens New Window
  (Close window to return to this page)

> To View Educational Specifications Click Here
  Opens New Window
  (Close window to return to this page)


> View Project Schedule
  Opens Projects Controls Master Schedules Webpage

> View Five-Year Plan
  Opens Current Five-Year Plan Webpage

School District of
Palm Beach County Florida
Department of Program Management
Program Management Projects
Monthly Progress Report
Suncoast High Replacement


The Project

This project is included on the 2004 referendum project list. It will be a comprehensive modernization and replacement of the existing Suncoast High. It will be relocated from the existing campus and built adjacent to the new JFK Middle School. In phase III, a stadium will also be constructed. Phase IV is the offsite roadwork and traffic signals. 

Project Status - Week ending July 22, 2011
Phase I Building pad,
Phase II Buildings 1-6
Phase III Site, athletic fields,parking and drives,stadium.
phase IV Off-site road work. Congress Ave. and 13th Street

Building 1 (Administration/Media):
Substantial completion and TCO achieved 4-23-10.

Building 2 (Dining area/Kitchen):
Substantial completion and TCO achieved 4-28-10.

Building 3 (classrooms):
Substantial completion and TCO achieved 4-28-10.

Building 4 (auditorium):
Substantial completion and TCO achieved 4-29-10.

Building 5 (Gym):
Substantial completion and TCO achieved 5-7-10.

Building 6 (chillers):
Substantial completion and TCO achieved 5-7-10.


General notes:


Water meter installed April 16, 2010.



PHASE 3
SITE:
Complete


Site wall:
Complete.

Building 7 (home concession/restrooms);
TCO 4-26-10.

Buildings 8&9 (press box and elevator tower):
TCO 4-26-10.

Building 10 (visitor concession/restrooms)
TCO 4-26-10

Milestone dates:
Phase I (Building pad)
June 18, 2007: Notice to proceed
August 27, 2007: Completed

Phase II (Buildings 1-6)

November 20, 2007: Phase II GMP approved
December 5, 2007: Notice to proceed
December 21, 2007: Foundation column pads permit issued
January 25, 2008 Interior column pads completed
February 7, 2008 Building permit issued
March 1, 2008 Groundbreaking ceremony
March 31, 2008 Water Use Permit
April 7, 2008 SFWMD Storm Water Discharge permit issued.
May 22, 2008 Received 18th. street closure permission.
May 30, 2008 MOT in place (closing of 18th. St.)
Sept. 9,2008 Church demolition complete.
Sept. 18,2008 SFWMD permit.
Feb.8,2010 City of Riviera Beach issued sewer permit
April 25, 2010 Water meter fee paid.
May 7, 2010 TCO received

Phase III (site work, athletic fields, stadium)

June 9, 2008 18th. Street closed.
June 9, 2008 Broadmoor Apts. demo in progress
June 9, 2008 1:30PM Pre-bid at project site.
Aug. 14,2008 GMP submitted
Sept.18,2008 SFWMD permit
TBD Army Corps permit issued.
Nov.12, 2008 GMP approved
Nov. 25,2008 Notice to proceed
Jan. 26, 2009 Dewatering permit.
Mar. 31, 2009 City of Riviera Utilities permit (Water)
July 17, 2009 Modified water use permit received.
Feb. 5, 2010 CRB approved Water/Sewer taps
Dec. 1, 2010 Start site wall

Phase IV (off site road modifications)

Feb. 3, 2010 Board approved GMP
June 16, 2010 Notice to Proceed
June 15, 2010 Palm Beach county ROW permit received
June 21, 2010 Pre-Con with County
June 29, 2010 City of Riviera Beach permit received
July 8, 2010 Pre-Con with Riviera Beach
Nov. 08, 2010 Congress,13th. and Jake open for traffic.


Congress Ave.
Complete
Permit Close out in progress

13th. Street:
Complete
Permit Close-out in progress.

Jake lane:
Complete
Permit close-out in progress.

This is the Final Report for Suncoast 


Project Contact List for Suncoast High Replacement
Contact Title Company Business Phone E-Mail
Glen Armbruster Sr. Project Admin. SDPBC-Capital Projects Group/Facility Services 561-882-1918 glen.armbruster@palmbeachschools.org
  Project Coord.      
  Project Field Rep.      
Mark Sagovac AP for Construction SDPBC    
Linda Cartlidge Principal SDPBC   lcartlidge@palmbeach.k12.fl.us
Wayne Gent Area Superintendant SDPBC    

 

>Back to Top